Live version on November 16th, release on December 3rd
One site in four languages, on Next.js and Contentful. The templates are finished by November 6th, the final content goes in from November 9th to 13th, then it is tested on the live version. Dates proposed on October 26th, to confirm with development.
Six changes since October 19th, and what each one changes
The Shift view walks through them: Exec.
| Change | What it changes | For whom |
|---|---|---|
| Loop names set: Advise, Build, Operate, ProvePortfolio draft 5, October 23rd | One Services template runs in the preprod. Implement becomes Build, Prove is a new page, and the four are drawn as one loop. | Design, development |
| Portfolio draft 5 of October 23rdRead and compared on October 26th | 24 capabilities, 6 personas, Banking and CPG renamed (Agriculture becomes Agribusiness, confirmed on October 27th), four awards for About. It also proposes Challenges, Tax and offer pages in the menu: proposed after release. Portfolio | Content, design, development |
| Portfolio frozen at the Shift of October 27thProposed for decision | Draft 5 goes live, except its menu additions. Later changes wait until after December 3rd. | Everyone |
| Publish what is right, then enrichAgreed on October 26th | Reviewed pages go live as they stand. What is announced, the Loop first, stays fixed. | Topic owners |
| Country pages need an ownerNew workstream | 29 country pages open in content-web on the France model, offices pre-filled. Owners named by November 3rd, content by November 20th. | Subsidiaries |
| One entry point for requests after launchBeing set up | A request form in ClickUp: bugs fixed first, features planned. | Everyone |
Critical path: templates first, then content, SEO and tests
Each step waits for the one before it. Order given by development on October 26th; dates proposed on October 26th, to confirm with development. The plan of September 24th is in the archive.
In parallel, ready before the test rounds: HubSpot forms, site search, the redirect map from the old URLs.
Actions to hold December 3rd
The sequence
Eleven decisions to take
The earlier these are settled, the less is rebuilt.
/es/ubicaciones/francia or /es/locations/france. To settle before pages multiply and old URLs are redirected.What is built, and what the release depends on
A built template still has its own list of fixes and checks before it goes to production.
In place
- Next.js front end, shared UI library, Contentful connected
- The 20 mockups built with demo content and CMS media
- Three-entry menu with its Featured block, four languages (EN, FR, ES, PT)
- Main animations and shared components
- First code review and CMS model review, done on October 26th
Still to do before release
- Final content and translations, loaded into the CMS
- Visual fixes, broken links and a full mobile test round
- HubSpot forms, built by the website team, then embedded in the pages
- Site search, destination pages and filters
- SEO and GEO pass on the real content, redirects from the old URLs
- The decisions listed above
| Step | Plan of September 24th | October 26th |
|---|---|---|
| Development | Sep 21st to Oct 9th, 15 working days | 20 templates built in Next.js on a new preprod, with demo content |
| Alpha | Oct 9th, on keyrus-redesign.netlify.app | The build runs on keyrus-ai.netlify.app; the dev link in the plan is updated |
| UAT round 1 | Oct 15th to 29th | Test rounds from November 16th, on the live version (proposed) |
| Beta and UAT round 2 | Oct 29th to Nov 26th | Live version with most content on November 16th (proposed), see the plan above |
| Release | Dec 3rd | Dec 3rd, confirmed by development on October 26th |
20 templates: 5 to fix, 2 to test, 13 to validate
Status from the development tracking of October 26th. "To validate" means built, waiting for a content or business sign-off.
Three Featured links return a 404; content and journeys to finish.
Full visual test, team animation cycle included; final content.
Contact details and social links are test data; brands, events, form.
Last period of the timeline repeated in the mockup; story to validate.
CRM connection, routing by country, anti-spam, consent.
Business content and regulatory references to validate.
Translations, link destinations, the three other capabilities.
Data card text inconsistent; card rotation speed; Loop, FAQ and form.
Partner ranking and content; 44 partners in the corporate presentation V2. Partner page template added to the Figma on November 5th, to build.
Featured block to realign on the mockup; links and filters.
"Learn more" not clickable; tags and resource destinations.
"Learn more" not clickable; country filter; video hosting.
Real dates, time zones, countries, archive, sign-up links.
Final text, author, tags, related links, form.
Client and logo approval, figures.
Difference with a use case that names its client; final content.
Real sign-up, date, place and speakers.
Role before and after the event; link with registration.
Final video, subtitles, transcript, hosting.
Redirect after sign-up and access rule for the video.
The route through the preprod
Eight stops, in this order. Each one opens the page as it runs today, with demo content.
The 34 menu pages in preprod
Services still follow the former Advise, Implement, Operate model in the mockups and the preprod: see the decisions above. Checked by HTTP request on each page, October 26th.
Three related projects
What waits until after release
Other group sites
- Proposal from development: reuse the same base for other group sites, with the shared UI library and one configuration per site
- Which sites, in what order and with which budget: to define after the release
CMS
- The site launches on Contentful
- CMS choice for 2027, proposed timing: audit in February, switch in May
- Development tracking, updated October 26th, 2026 (Erwan): keyrus-ai-suivi-dev.netlify.app
- Preprod: keyrus-ai.netlify.app, pages checked one by one on October 26th
- Content review tool: content-web.keyrus.pro, read on October 26th
- What the portfolio changes on the site: Portfolio; Loop names from portfolio draft 5 of October 23rd
- The full plan until October 26th (decisions D1 to D11, timeline of September 24th, menu, HOM and audit): plan.keyrus.pro/archive